Tennessee

IFT Featured Tennessee Job: Dual 4” Carbon Steel Pipe Linestops - 5.0 out of 5 based on 3 reviews

User Rating: 5 / 5

Star ActiveStar ActiveStar ActiveStar ActiveStar Active

Dual 4” Carbon Steel Pipe Linestops in Nashville, TN.

Dual 4” Carbon Steel Pipe Linestops in Nashville, TN.

Job Status: Successful and Completed
Job Date: July 16, 2018
JOB LOCATION: Nashville, TN.
PROJECT: Vanderbilt

1 – Mobilization – Prep / Travel to Job Site

ltem l Linestop 4” Carbon Steel Pipe
2 – 4” Linestop fitting for Carbon Steel Chilled Water (100 PSI or Less) (Fitting provided by IFT and weld on by Contractor)
2 – Installation of temporary valve with air test.
2 – Hot Taps to allow for linestop entry
2 – Insertion of linestop for 1 day
2 – 3/4” Tap on contractor supplied and installed materials for blow down and equalizing pressure to remove linestop. (If Needed)
2– Removal of Linestop, install completion plug and cap

OR Call

Nationwide: 1-800-221-3332

Local: 1-951-926-4849

Fax: 1-951-926-2334

IFT Featured Tennessee Job: 8" x 6" Hottaps and pressure test on chill water in Nashville, Tennessee - 5.0 out of 5 based on 7 reviews

User Rating: 5 / 5

Star ActiveStar ActiveStar ActiveStar ActiveStar Active

8" x 6" Hottaps and pressure test on chill water carbon steel pipeline in Nashville, Tennessee

8” x 6” Hottaps and pressure test on chill water carbon steel pipeline in Nashville, Tennessee job completed with valves in place

Job Status: Successful and Completed
Job Date: October 3, 2018
JOB LOCATION: Nashville, TN
PROJECT: 8 x 6 Hottap and pressure test on chill water in Nashville, Tennessee

1 – Travel to site

ITEM 1 – 6” Hot Tap
2 – 6” Hot Tap on Carbon Steel Chilled Water (100 PSI or Less) Through Contractor furnished and preinstalled materials.
2 – Air Testing of tapping equipment (ANSI150# Flange)

OR Call

Nationwide: 1-800-221-3332

Local: 1-951-926-4849

Fax: 1-951-926-2334

Chiller Plant Improvements Hottaps, Thermo-well Installations & Pipe Freezing Services

Job Status: Successful and Completed
Job Date: May 15, 2013
Location: Oak Ridge, TN
Job Specifics: Chillers – 6 Total

ITEM 1 – 24” Freezes ( No Flow through pipe ) 12 – 24” Pipe freezing on Tower Water carbon steel pipeline ( Horizontal ) 8 hours hold time for freeze while you make pipeline modifications Estimated 30 – 160 LT. Dewars per freeze

ITEM 2 – 12” Freezes ( No Flow through pipe ) 12 – 12” Pipe freezing on Chilled Water carbon steel pipeline ( Vertical ) 8 hours hold time for freeze while you make pipeline modifications Estimated 12 – 160 LT. Dewars per freeze

Item 3 – 2” Hot Taps – Drains 4 – 2” Hot Taps on bottom of pipes for checking freeze and draining ( Materials and installation by customer)
4 – Air testing of tapping assembly  

Item 4 – 3/4” Hot Taps 4 – 3/4” Hot Taps on top of pipes for air release ( Materials and installation by customer)
4 – Air testing of tapping assembly                                              

Chilled Water Pumps – 6 Total

ITEM 5 – 24” Freezes ( No Flow through pipe ) 3 – 24” Pipe freezing on Chilled Water Return carbon steel pipeline ( Horizontal ) 8 hours hold time for freeze while you make pipeline modifications Estimated 30 – 160 LT. Dewars per freeze

ITEM 6 – 16” Freezes ( No Flow through pipe ) 3 – 16” Pipe freezing on Chilled Water Supply carbon steel pipeline ( Horizontal ) 8 hours hold time for freeze while you make pipeline modifications Estimated 20 – 160 LT. Dewars per freeze

Item 7 – 2” Hot Taps – Drains 1 – 2” Hot Taps on bottom of pipes for checking freeze and draining ( Materials and installation by customer)
1 – Air testing of tapping assembly

Item 8 – 3/4” Hot Taps 1 – 3/4” Hot Taps on top of pipes for air release ( Materials and installation by customer)
1 – Air testing of tapping assembly                             

Thermo-wells and Hot Taps

Item 9 – ¾” Thermo-well Taps – Carbon Steel
6 – ¾”-Thermo-lets, for chilled waterlines Carbon Steel ( Welding by customer)
6 – Temporary installation of access valve and hot taps
6 – Insertion of your provided ¾” (IP) wells – please provide office with nut size
Item 10 – ¾” Hot Taps – Carbon Steel – Same travel as Thermo-wells
10 – Pressure testing of assemblies
10 – ¾” Hot Taps through your provided and installed full port ball valves (IP), for Chilled Water Carbon Steel

OR call

Nationwide: 1-800-221-3332

Local: 1-951-926-4849

Fax: 1-951-926-2334

IFT Featured Tennessee Job: 18” and 14" Linestops Carbon Steel - Mill Water Pipe - 5.0 out of 5 based on 7 reviews

User Rating: 5 / 5

Star ActiveStar ActiveStar ActiveStar ActiveStar Active

18” and 14" Indoor Linestops Carbon Steel - Mill Water Pipe

14" and 18" Indoor Linestop In Nashville, Tennessee

Job Status: Successful and Completed
Job Date: June 15, 2015
JOB LOCATION: Nashville, TN PROJECT: Carlex

Job Specifics: 1 – Travel to site to scrap and try to clean pipe to help perform a proper seal.
1 – Travel to site to perform indoor linestops
1 – Travel to site remove and complete indoor linestops

ltem l Linestop Indoor 18” Carbon Steel - Mill Water Pipe – Horizontal
1 – Indoor 18” Linestop Using a 2LBin/IFT Split Weld Tee for Carbon Steel Mill Water Pipeline (60 PSI or less) (Provided by IFT and weld on by Contractor)
1 – Installation of temporary valve with air test.
1 – Hot Taps to allow for linestop entry
1 – Insertion of 18” linestop
1 – 2” Taps on contractor supplied and installed materials for blow down and equalizing pressure to remove linestop.
1 – 2 Day Hold while you make pipe modifications.
1 – Removal of Linestops, install completion plug and Blind Flange

ltem 2 Linestop 14” Carbon Steel - Mill Water Pipe – Vertical
1 – 14” Linestop Using a 2LBin/IFT Split Weld Tee for Carbon Steel Mill Water Pipeline (60 PSI or less) (Provided by IFT and weld on by Contractor)
1 – Installation of temporary valve with air test.
1 – Hot Taps to allow for linestop entry
1 – Insertion of 18” linestop
1 – 2” Taps on contractor supplied and installed materials for blow down and equalizing pressure to remove linestop.
1 – 2 Day Hold while you make pipe modifications.
1 – Removal of Linestops, install completion plug and Blind Flange