Dual 4” Carbon Steel Pipe Linestops in Nashville, TN.

Dual 4” Carbon Steel Pipe Linestops in Nashville, TN.

Job Status: Successful and Completed
Job Date: July 16, 2018
JOB LOCATION: Nashville, TN.
PROJECT: Vanderbilt

1 – Mobilization – Prep / Travel to Job Site

ltem l Linestop 4” Carbon Steel Pipe
2 – 4” Linestop fitting for Carbon Steel Chilled Water (100 PSI or Less) (Fitting provided by IFT and weld on by Contractor)
2 – Installation of temporary valve with air test.
2 – Hot Taps to allow for linestop entry
2 – Insertion of linestop for 1 day
2 – 3/4” Tap on contractor supplied and installed materials for blow down and equalizing pressure to remove linestop. (If Needed)
2– Removal of Linestop, install completion plug and cap

OR Call

Office hours 7:30 – 5:00 Central time

Nationwide: 1-800-221-3332

Emergency Services Available .

 

 

IFT Featured Tennessee Job: 8" x 6" Hottaps and pressure test on chill water in Nashville, Tennessee - 5.0 out of 5 based on 7 reviews

User Rating: 5 / 5

Star ActiveStar ActiveStar ActiveStar ActiveStar Active

8" x 6" Hottaps and pressure test on chill water carbon steel pipeline in Nashville, Tennessee

8” x 6” Hottaps and pressure test on chill water carbon steel pipeline in Nashville, Tennessee job completed with valves in place

Job Status: Successful and Completed
Job Date: October 3, 2018
JOB LOCATION: Nashville, TN
PROJECT: 8 x 6 Hottap and pressure test on chill water in Nashville, Tennessee

1 – Travel to site

ITEM 1 – 6” Hot Tap
2 – 6” Hot Tap on Carbon Steel Chilled Water (100 PSI or Less) Through Contractor furnished and preinstalled materials.
2 – Air Testing of tapping equipment (ANSI150# Flange)

OR Call

Office hours 7:30 – 5:00 Central time

Nationwide: 1-800-221-3332

Emergency Services Available .

 

 

Chiller Plant Improvements Hottaps, Thermo-well Installations & Pipe Freezing Services

Job Status: Successful and Completed
Job Date: May 15, 2013
Location: Oak Ridge, TN
Job Specifics: Chillers – 6 Total

ITEM 1 – 24” Freezes ( No Flow through pipe ) 12 – 24” Pipe freezing on Tower Water carbon steel pipeline ( Horizontal ) 8 hours hold time for freeze while you make pipeline modifications Estimated 30 – 160 LT. Dewars per freeze

ITEM 2 – 12” Freezes ( No Flow through pipe ) 12 – 12” Pipe freezing on Chilled Water carbon steel pipeline ( Vertical ) 8 hours hold time for freeze while you make pipeline modifications Estimated 12 – 160 LT. Dewars per freeze

Item 3 – 2” Hot Taps – Drains 4 – 2” Hot Taps on bottom of pipes for checking freeze and draining ( Materials and installation by customer)
4 – Air testing of tapping assembly  

Item 4 – 3/4” Hot Taps 4 – 3/4” Hot Taps on top of pipes for air release ( Materials and installation by customer)
4 – Air testing of tapping assembly                                              

Chilled Water Pumps – 6 Total

ITEM 5 – 24” Freezes ( No Flow through pipe ) 3 – 24” Pipe freezing on Chilled Water Return carbon steel pipeline ( Horizontal ) 8 hours hold time for freeze while you make pipeline modifications Estimated 30 – 160 LT. Dewars per freeze

ITEM 6 – 16” Freezes ( No Flow through pipe ) 3 – 16” Pipe freezing on Chilled Water Supply carbon steel pipeline ( Horizontal ) 8 hours hold time for freeze while you make pipeline modifications Estimated 20 – 160 LT. Dewars per freeze

Item 7 – 2” Hot Taps – Drains 1 – 2” Hot Taps on bottom of pipes for checking freeze and draining ( Materials and installation by customer)
1 – Air testing of tapping assembly

Item 8 – 3/4” Hot Taps 1 – 3/4” Hot Taps on top of pipes for air release ( Materials and installation by customer)
1 – Air testing of tapping assembly                             

Thermo-wells and Hot Taps

Item 9 – ¾” Thermo-well Taps – Carbon Steel
6 – ¾”-Thermo-lets, for chilled waterlines Carbon Steel ( Welding by customer)
6 – Temporary installation of access valve and hot taps
6 – Insertion of your provided ¾” (IP) wells – please provide office with nut size
Item 10 – ¾” Hot Taps – Carbon Steel – Same travel as Thermo-wells
10 – Pressure testing of assemblies
10 – ¾” Hot Taps through your provided and installed full port ball valves (IP), for Chilled Water Carbon Steel

OR call

Office hours 7:30 – 5:00 Central time

Nationwide: 1-800-221-3332

Emergency Services Available .

 

 

IFT Featured Tennessee Job: 18” and 14" Linestops Carbon Steel - Mill Water Pipe - 5.0 out of 5 based on 7 reviews

User Rating: 5 / 5

Star ActiveStar ActiveStar ActiveStar ActiveStar Active

18” and 14" Indoor Linestops Carbon Steel - Mill Water Pipe

14" and 18" Indoor Linestop In Nashville, Tennessee

Job Status: Successful and Completed
Job Date: June 15, 2015
JOB LOCATION: Nashville, TN PROJECT: Carlex

Job Specifics: 1 – Travel to site to scrap and try to clean pipe to help perform a proper seal.
1 – Travel to site to perform indoor linestops
1 – Travel to site remove and complete indoor linestops

ltem l Linestop Indoor 18” Carbon Steel - Mill Water Pipe – Horizontal
1 – Indoor 18” Linestop Using a 2LBin/IFT Split Weld Tee for Carbon Steel Mill Water Pipeline (60 PSI or less) (Provided by IFT and weld on by Contractor)
1 – Installation of temporary valve with air test.
1 – Hot Taps to allow for linestop entry
1 – Insertion of 18” linestop
1 – 2” Taps on contractor supplied and installed materials for blow down and equalizing pressure to remove linestop.
1 – 2 Day Hold while you make pipe modifications.
1 – Removal of Linestops, install completion plug and Blind Flange

ltem 2 Linestop 14” Carbon Steel - Mill Water Pipe – Vertical
1 – 14” Linestop Using a 2LBin/IFT Split Weld Tee for Carbon Steel Mill Water Pipeline (60 PSI or less) (Provided by IFT and weld on by Contractor)
1 – Installation of temporary valve with air test.
1 – Hot Taps to allow for linestop entry
1 – Insertion of 18” linestop
1 – 2” Taps on contractor supplied and installed materials for blow down and equalizing pressure to remove linestop.
1 – 2 Day Hold while you make pipe modifications.
1 – Removal of Linestops, install completion plug and Blind Flange