Job Status: Successful and Completed
Job Date: December 1, 2017
JOB LOCATION:  Laguna Niguel, CA.
PROJECT: 12” Linestop
Job Specifics:
Item I: 12”Linestop® on A/C Water Main Under 120 psi – No By-pass
2 – Mobilization - Prep / Travel to site – One to Set L/S & One to Remove L/S
1 – 12” x 12” Linestop® Fitting for A/C Pipe (O.D. 14.32”)
(JCM 432 Style - Stainless Steel w/SS Bolts and Carbon Steel Linestop Flange)
1 – Installation of temporary valve with air test.
1 – Hot Tap to allow for Linestop® entry
1 – Insertion of 12” Linestop® – held for up to 3 days while Contractor performs Pipeline modifications
1 – Removal of Linestop® installation of completion plugs and Blind Flanges Installation of Blow-off assemblies as required for removal of Linestop®