1-800-221-3332
Contact us Today!

 Anchorage, AK • Delaware, DE • Oklahoma City, OK • Nashville, TN • New Orleans, LA • Houston, TX

Hawaii

Multiple 10", 16", 20" 24" Linestops and Valve Installation Services

Job Status: Successful and Completed
Job Date: June 4. 2012
Location: Schofield Barracks- Hawaii
Job Specifics: 

2 -16" Linestop fittings for domestic waterlines at or under 150PSI
2 -16" Linestops held for up to 2 days while you perform pipeline modifications.
2 - Remove stops and install completion plugs and blind flanges Valves #
2- 20" & 16" Linestops
1 - 20" Linestop fitting for domestic water main at or under 150PSI
1 - 20" Linestop held for up to 2 days while you perform pipeline modifications.
1 - Remove stop and install completion plug and blind flange.
1 - 16" Linestop fitting for domestic waterlines at or under 150PSI
1 - 16" Linestop held for up to 2 days while you perform pipeline modifications.
1 - Remove stop and install completion plugs and blind flanges Valve #3 - 24" - 20" - 10" Linestops
2 - 24" Linestop fittings for domestic waterlines at or under 150PSI
2 - 24" Linestops held for up to 2 days while you perform pipeline modifications.
2 - Remove stops and install completion plugs and blind flanges
1 - 20" Linestop fitting for domestic waterline at or under 150PSI
1 - 20" Linestop held for up to 2 days while you perform pipeline modifications
1 - Remove stop and install completion plug and blind flange
1 - 10" Linestop fitting for domestic waterlines at or under 150PSI
1 - 10" Linestop held for up to 2 days while you perform pipeline modifications
1 - Remove stop and install completion plugs and blind flanges Valve #6- 24" Linestops
2 - 24" Linestop fittings for domestic waterlines at or under 150PSI
2 - 24" Linestops held for up to 2 days while you perform pipeline modifications
2 - Remove stops and install completion plugs and blind flanges Valve #7- 24" Linestops
2 - 24" Linestop fittings for domestic waterlines at or under 150PSI
2 - 24" Linestops held for up to 2 days while you perform pipeline modifications
2 - Remove stops and install completion plugs and blind flanges (contractor to Cut & Cap existing 8" line) Valve #8- 24" Linestops
2 - 24" Linestop fittings for domestic waterlines at or under 150PSI
2 - 24" Linestops held for up to 2 days while you perform pipeline modifications
2 - Remove stops and install completion plugs and blind flanges Valve #9 - 16" Linestops
2 - 16" Linestop fittings for domestic waterlines at or under 150PSI
2 - 16" Linestops held for up to 2 days while you perform pipeline modifications
2 - Remove stops and install completion plugs and blind flanges
** Above pricing includes one mobilization of equipment with one technician for up to one week stay (?days) to one island ; with up to two linestops completed. Additional Mobilization Pricing is as follows: Technician Travel/Mobilization
1 - Mobilization and Travel to Hawaii for one technician per 7 day week -up to 2 linestops completed. Equipment Mobilization
1 - Moving equipment on and off the island -Any stand-by time not caused by 1FT, including safety courses, orientations, etc. will be billed per technician for straight time.
Linestop® • Valve Inserting • Pipefreeze® • Large Tapping

OR Call

Office hours 7:30 – 5:00 Central time

Nationwide: 1-800-221-3332

Emergency Services Available .

 

 

Go to top